AI 导读
Anthropic 正在洽谈租用位于埃德蒙顿附近、由 920MW 燃气电站供电的超大规模数据中心园区。该园区由卡尔加里的 Beacon Data Centers 开发,Sturgeon County 场地规划有 4 个 AI 计算数据厅,预计于本季度开工并在 2027 年底投入使用。
正文 · 原文
Anthropic is negotiating to lease a hyperscale data centre campus near Edmonton powered by a dedicated 920MW gas plant.
Calgary-based Beacon Data Centers is developing the Sturgeon County site, which its filings show will hold 4 data halls for AI computing.
Alberta’s Utilities Commission approved that plant on October 23, with construction due this quarter and service in late 2027.
That would give the campus about double the power of the 420MW Nova Scotia site, where Anthropic signed a 20-year lease.